- Details
- 1823 LINWOOD STREET NW
- Description
- BUILDING 10 FOR 1 NEW (6) UNIT MULTI-FAMILY BUILDING 101-106
Person Details
BONAVENTURE CONSTRUCTION
- Roles
- Contractor, Interested Party
- Address
-
3425 BOONE RD S
SALEM OR 97317
CAMERON MEMMOTT
- Roles
- Contact
- Address
-
3425 BOONE RD SE
SALEM OR 97317
SABINA FRANK
- Roles
- Contact
- Address
-
3425 SE BOONE RD
SALEM OR 97317
MWSH WEST SALEM LLC
- Roles
- Owner
- Address
-
3425 BOONE RD SE
SALEM OR 97317
SHAWN EVJEN
- Roles
- Applicant, Contact, Paid By
- Address
-
3425 BOONE RD SE
SALEM OR 97317
Property Details
Info
- Contractors' Construction Board #
- 186852
- Valuation
- 1400372.62
- Type of Construction
- V B
- Ending total # units in building
- 6
- Sq Ft - finished
- 9436.00
- Number of Floors
- 2
- Zoning
- RM2
- In Floodplain?
- No
Action Details
Application Intake
-
Application Intake
- Status:
- Accept Plans
- Completed Date:
- 8/17/2023
- Assigned Staff:
- Permit Technician
- View Details
Info
Final B&S Inspections
-
Final Structural Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Structural
-
Final PW Regulatory Review
- Status:
- Open
- Assigned Staff:
- PW Coordinator
-
Final Zoning Inspection
- Status:
- Open
- Assigned Staff:
- Planner
-
Final Landscape Inspection
- Status:
- Open
- Assigned Staff:
- Planner
-
Final Fire Inspection
- Status:
- Open
- Assigned Staff:
- Deputy Fire Marshal
Info
Inspections-Building
-
Footing/Setback Inspection
- Status:
- Approved
- Completed Date:
- 1/31/2025
- Assigned Staff:
- Roberto Rios
- View Details
-
Foundation Inspection
- Status:
- Approved
- Completed Date:
- 1/31/2025
- Assigned Staff:
- Roberto Rios
- View Details
-
Grout/Rebar Inspection
- Status:
- Approved
- Completed Date:
- 1/31/2025
- Assigned Staff:
- Inspector Structural
- View Details
-
Underfloor Framing Inspection
- Status:
- Approved
- Completed Date:
- 4/14/2025
- Assigned Staff:
- Roberto Rios
- View Details
-
Shear Wall Inspection
- Status:
- Approved
- Completed Date:
- 5/16/2025
- Assigned Staff:
- Matthew Smith
- View Details
-
Roof Nailing Inspection
- Status:
- Approved
- Completed Date:
- 5/19/2025
- Assigned Staff:
- Roberto Rios
- View Details
-
Framing Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Structural
-
Insulation Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Structural
-
Sheetrock Nailing Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Structural
-
Masonry Fireplace Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Structural
-
Ufer Ground Inspection
- Status:
- Approved
- Completed Date:
- 1/31/2025
- Assigned Staff:
- Roberto Rios
- View Details
Info
Plan Review
-
BAS Plan Review
- Status:
- Approved
- Completed Date:
- 3/19/2024
- Assigned Staff:
- Matthew O'Donnell
- View Details
-
BAS Engineer Review
- Status:
- Approved
- Completed Date:
- 3/23/2024
- Assigned Staff:
- Al Rossi
- View Details
-
Planning Plan Review
- Status:
- Approved
- Completed Date:
- 3/18/2024
- Assigned Staff:
- Jamie Donaldson
- View Details
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 5/1/2024
- Assigned Staff:
- Matt Olney
- View Details
-
Fire Review
- Status:
- Approved
- Completed Date:
- 3/19/2024
- Assigned Staff:
- Justin Guinan
- View Details
-
Landscape Review
- Status:
- No review required
- Completed Date:
- 8/25/2023
- Assigned Staff:
- Jamie Donaldson
- View Details
-
Final Review
- Status:
- Approved
- Completed Date:
- 4/30/2024
- Assigned Staff:
- PAC Shipping
- View Details