Development Permit Details
21 116377 00 PC
- Number
- 21 116377 00 PC
- Type
- Public Construction - PW - zzArchive - SUB - Major Facilities - Water/Sewer/Street/Storm
- Status
- Completed
- Details
- PC_STRONG HEIGHTS
- Description
- Subdivision to create 29 SF lots
Person Details
WESTECH ENGINEERING INC
- Roles
- Engineer
- Address
-
3841 FAIRVIEW INDUSTRIAL DR SE SUITE 100
SALEM OR 97302-1192
WILLAMETTE VALLEY EXCAVATING LLC
- Roles
- Contractor
- Address
-
PO BOX 12861
SALEM OR 97309
Property Details
Action Details
Agreements
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 3/7/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 3/17/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Improvement Agreement
- Status:
- Approved
- Completed Date:
- 11/4/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
Info
Application Intake
-
Assign Bin Number
- Status:
- Open
- Assigned Staff:
- PW Coordinator
-
Make Ready To Issue (DS)
- Status:
- Approved
- Completed Date:
- 3/17/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 3/2/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
-
Fire Review
- Status:
- Approved
- Completed Date:
- 11/29/2021
- Assigned Staff:
- Fire Plan Review
- View Details
-
Landscape Review
- Status:
- Closed
- Completed Date:
- 3/2/2022
- Assigned Staff:
- Curtis Pellatz
- View Details
Info
PW Inspections
-
10 month warranty inspection
- Status:
- In Review
- Assigned Staff:
- PW Inspector
- View Details
-
Sewer Tap Installation
- Status:
- Completed by City
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Sewer
- View Details
-
As-Built Review
- Status:
- Complete
- Completed Date:
- 11/16/2022
- Assigned Staff:
- PW Engineering
- View Details
-
Acceptance
- Status:
- Accepted
- Completed Date:
- 10/25/2022
- Assigned Staff:
- PW Engineering
- View Details
-
10-month TV Inspection
- Status:
- Open
- Assigned Staff:
- Christopher Ratcliff
- View Details
-
ADA Ramps
- Status:
- Approved
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Inspector
- View Details
-
Sewer Pressure Test
- Status:
- Approved
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Sewer
- View Details
-
Sewer TV Inspection
- Status:
- Complete
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Sewer
- View Details
-
Storm TV Inspection
- Status:
- Complete
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Sewer
- View Details
-
Stormwater Treatment Inspection
- Status:
- Approved
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Inspector
- View Details
-
Erosion Control Inspection
- Status:
- Approved
- Completed Date:
- 10/31/2022
- Assigned Staff:
- Link Chapman
- View Details
-
Street Trees
- Status:
- Closed
- Completed Date:
- 10/31/2022
- Assigned Staff:
- PW Inspector
- View Details
Info
PW Water Inspections
-
Chlorination <=12"
- Status:
- Completed by City
- Completed Date:
- 9/20/2022
- Assigned Staff:
- William Swint
- View Details
-
Water Tap Installation
- Status:
- Completed by City
- Completed Date:
- 8/18/2022
- Assigned Staff:
- Donald Lovas
- View Details
-
Water Tap Installation
- Status:
- Completed by City
- Completed Date:
- 8/18/2022
- Assigned Staff:
- Donald Lovas
- View Details
Info