Process Details
- Description
- DS Plan Review
- Folder Number
- 25 111796 00 PL
- Folder Details
- PL_NORTHPLACE APTS 2_Property Line Adjustment
- Permit Type
- Plats - Lot Line Adjustment
- Scheduled Date
- 8/20/2025
- Assigned Staff
- Tiffany Russell
Process Comments
Comment Number | Scheduled Date | Comment Date | Staff | Result | Comment |
---|---|---|---|---|---|
1 | 6/23/2025 | Curtis Pellatz | In Review | Routed to City Surveyor | |
2 | 6/23/2025 | Curtis Pellatz | Info Requested | Discovered that the provided Title Report is not for the correct property. Requested new Title Report for the Phase II properties. | |
3 | 7/1/2025 | Curtis Pellatz | Info Received | Received corrected Title Reports. Routed to City Surveyor in Session. | |
4 | 7/1/2025 | Curtis Pellatz | Info Received | Added by Review Cycle process | |
5 | 7/9/2025 | Curtis Pellatz | Info Requested | 07-09-25: AKS Engineering has requested that this review be placed on "Hold". See email from Robert Carter below: Good Morning Everyone, Kyle, Matthew, and Curtis, Our client has decided to change up how we are going forth with the location of the adjusted line for this project. Please put the Cities review of the PLA materials on hold. We still will be going through with the previously sent right-of-way dedication though. Thank You, Robert Carter, Survey Technician AKS ENGINEERING & FORESTRY, LLC |