1 |
|
12/12/2022 |
Justin Guinan |
Corrections |
1. Service and install FE per approved plans.
2. Install exterior emergency lights per approved plans.
3. Install key safe at rear door near FDC.
4. Install riser room and FACP identification on rear door near FDC.
5 Install FACP and Riser Room identification on interior doors as discussed.
6. Verify that the vault control valve is chained.
7. Replace round exit door handles with lever handles. |
2 |
|
12/22/2022 |
Justin Guinan |
Corrections |
1. Add FDC sign near FDC connection.
2. Install interior exit sign per approved plans.
3. Uncover sprinkler heads above bay door.
4. Provide 90 minute egress light test to TCE. |
3 |
|
12/30/2022 |
Justin Guinan |
Corrections |
1. Provide 90 minute egress light test to TCE.
2. Add needed egress lighting building. |
4 |
|
1/3/2023 |
Justin Guinan |
Corrections |
Needs to reschedule.
1. Provide 90 minute egress light test to TCE.
2. Add needed egress lighting building at FDC door.
3. Add egress lighting in parts room. |
5 |
|
1/20/2023 |
Robert Johnson |
Approved |
All previous items listed have been corrected.
May apply for CO. |