1 |
|
3/15/2022 |
Sara Roth |
Inspected |
Partial cover inspection. Highlighted on approved plans in green. Thrust block near FDC not poured - no cover this area. |
2 |
|
3/18/2022 |
Sarah Poet |
Inspected |
Partial Cover - plans marked in yellow
Thrust block previously noted by DFM Roth is abated. |
3 |
|
4/1/2022 |
Sean Mansfield |
Inspected |
Verified plans on site. System pumped up to 202 psi at 11:08 a.m. and held the pressure until 1:12 p.m. There was no drop in pressure. System drained down. Plans marked and signed. |
4 |
|
4/4/2022 |
Sara Roth |
Approved |
Witnessed flushing of the underground fire service line and the FDC - both passed clean. Temp C/O okay. Contractors Materials & Test Certificate for Underground Piping to be submitted to DFM. FM5 left business card. |