2 |
|
10/14/2021 |
Kimberli Fitzgerald
|
Approved |
per HCR21- 04; CONDITION 1: A qualified archaeological monitor shall be present during the deepest ground disturbing activity required for excavations up to 13 of soil into the subbase (native soils) for installation of the sanitary sewer connection on the west side of the site. Monitoring is also required for excavation of the backflow assembly vault near the driveway off of 23rd Street SE on the east side of the site.
CONDITION 2: An Inadvertent Discovery Plan (IDP) for both cultural resources and human remains shall be posted on site throughout construction and shall be utilized during shallow utility and foundation excavations. Should any resources be encountered during ground disturbing activity on the site, work shall cease, the site secured and this IDP shall be followed. |