Development Permit Details
21 123513 00 P
Permit- Number
- 21 123513 00 P
- Type
- Plumbing Permit - Commercial - New
- Status
- Finaled
- Details
- 1457 23RD STREET SE
- Description
- SITE UTILITIES - SALEM PUBLIC WORKS OPERATION BUILDING
Person Details
KORY RAY
- Roles
- Contact
- Address
-
550 SW 12TH AV STE 400
PORTLAND OR 97205-2300
LUKE GMAZEL
- Roles
- Contact
- Address
-
PO BOX 14300
CITY OF SALEM PUBLIC WORKS ENGINEERING
HOWARD S WRIGHT
- Roles
- Interested Party
- Address
-
1455 NW IRVING ST STE 400
PORTLAND OR 97209
K AND E EXCAVATING
- Roles
- Applicant, Contractor
- Address
-
3871 LANGLEY ST SE
SALEM OR 97317-9322
CITY OF SALEM-PUBLIC WORKS
- Roles
- Owner, Paid By
- Address
-
555 LIBERTY ST SE STE 325
SALEM OR 97301-3513
Property Details
Info
- Contractors' Construction Board #
- 128542
- Plumbing Contractor's License #
- 24-431PB
- Storm water pipe - Linear feet
- 1200
- Sanitary sewer pipe - Linear Feet
- 67
- Water service pipe - Linear Feet
- 200
- Footing Drain - Linear Feet
- 175
- Rain Drain - Linear Feet
- 369
Action Details
Application Intake
-
Application Intake
- Status:
- Accept Plans
- Completed Date:
- 2/10/2022
- Assigned Staff:
- Mareva Massey
- View Details
Info
Final B&S Inspections
-
Final Plumbing Inspection
- Status:
- Finaled
- Completed Date:
- 8/18/2023
- Assigned Staff:
- Matthew Smith
- View Details
Info
Inspections-Plumbing
-
Sewer - Underground Plumbing Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
- View Details
-
Storm - Underground Plumbing Inspection
- Status:
- Inspected
- Assigned Staff:
- Inspector Plumbing
- View Details
-
Underfloor Plumbing Inspection
- Status:
- Inspected
- Assigned Staff:
- Inspector Plumbing
- View Details
-
Top Out/Cover Plumbing Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
-
Shower Pan Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
-
Footing Drain Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
-
Rain Drain Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
-
Water Service Inspection
- Status:
- Inspected
- Assigned Staff:
- Inspector Plumbing
- View Details
-
Medical Gas Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
-
Backflow Device Inspection
- Status:
- Open
- Assigned Staff:
- Inspector Plumbing
Info
Plan Review
-
Plumbing Review
- Status:
- Approved
- Completed Date:
- 2/17/2022
- Assigned Staff:
- Matthew Smith
- View Details
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 2/10/2022
- Assigned Staff:
- Matt Olney
- View Details
-
Final Review
- Status:
- Approved
- Completed Date:
- 2/17/2022
- Assigned Staff:
- PAC Shipping
- View Details
-
Floodplain Development Review
- Status:
- Complete
- Completed Date:
- 2/11/2022
- Assigned Staff:
- Robin Dalke
- View Details