Development Permit Details
21 118343 00 CO
- Number
- 21 118343 00 CO
- Type
- Commercial Permit - DS - Commercial - New
- Status
- Completed
- Details
- CO - PW SHOPS COMPLEX SITE WORK- 1457 23RD STREET SE
- Description
- CIVIL SITE WORK - 50,000 SF OFFICE BUILDING & ASSOCIATED SITE WORK FOR THE CITY OF SALEM PUBLIC WORKS SHOPS COMPLEX PER SRC 41.150(a)(4), CITY PROJECT EXEMPT FROM SDCs
Person Details
DANIEL CHILDS
- Roles
- Applicant
- Organization
- HACKER ARCHITECTS
- Address
-
555 SE MLK BV STE 501
PORTLAND OR 97214
LUKE GMAZEL
- Roles
- Contact, Paid By
- Address
-
PO BOX 14300
CITY OF SALEM PUBLIC WORKS ENGINEERING
HOWARD S WRIGHT
- Roles
- Contractor
- Address
-
1455 NW IRVING ST STE 400
PORTLAND OR 97209
FRANCISCO LOPEZ
- Roles
- Paid By, Owner
- Address
-
555 LIBERTY ST NE
SALEM OR 97301
HACKER ARCHITECTS
- Roles
- Architect
- Address
-
1516 SE 3RD AV STE 500
SALEM OR
CITY OF SALEM-PUBLIC WORKS
- Roles
- Responsible Utility Billing Contact
- Address
-
555 LIBERTY ST SE STE 325
SALEM OR 97301-3513
Property Details
Info
- In Urban Service Area?
- Yes
- County Name
- Marion
- Subject to SDF?
- Yes
- Permits Required?
- Yes
- Proposed Developed Area
- 2.5
- Jurisdiction
- Salem
- Special Conditions
- Contractor to follow all State and Federal Regulations. Private Plumbing Permits are required for all on-site utility installation (Please contact Building & Safety 503-588-6256). Any work performed within Public Right-of-Way requires a separate "Work In ROW" permit (Please contact Ron Adkins or Van Tran at 503-588-6211).
- Water Service Level
- G0
- USGS Elevation
- 180
- PSI
- 66
- Install Domestic Water Meter?
- Yes
- Install Domestic Water Service Line
- Yes
- Domestic Water Meter Type
- Disk
- Domestic Water Service Line Size
- 2-inch
- Domestic Water Meter Size
- 2-inch
- Geo Review Req'd?
- No
- Erosion Control Permit Req'd?
- 1200-C
- Copy of DEQ Permit Submitted?
- Yes
- Adjacent to Waterway/Wetlands?
- No
- Excavation/Fill Permit Req'd
- No
- Install Irrigation Water Meter?
- No
- Install Irrigation Water Service Line
- No
- Irrigation Water Meter Type
- Disk
- Driveway Req'd
- New
- Driveway Width
- 35
- Driveway Location
- 23RD ST
- Driveway #2 Req'd
- None
- Driveway Closure Req'd
- No
- Driveway #2 Closure Req'd
- No
- Sidewalk Req'd?
- New
- Sidewalk Width
- 5
- Sidewalk Length
- 20
- Sidewalk Street Name
- 23RD ST
- Sidewalk Location
- Curb Line
- Sidewalk #2 Req'd?
- None
- Lane Closure Required
- None
- Storm?
- Connect
- Length of Storm Pipe
- 0
- Storm Location
- GSI facilities on site, connects to existing (replaced) CB in 23rd Street
- Storm Disconnect
- No
- Street Opening Required?
- No
- Storm Tap Type
- None
- Sewer Tap Order Quantity
- 1
- Sewer Tap Type
- Main
- Sewer Tap Size
- 6-inch
- Sewer Main Size
- 10-inch
- Sewer Main Pipe Material
- CO
- Sewer?
- Connection - Inside City
- Length of Sewer Pipe
- 67
- Sewer Location
- 6" SS, City forces to tap existing 10-inch main on property west of building site. See plans for location and details
- Is Floodplain Development Required?
- Ground Disturbing Activity
- Elevation Certificate Req'd?
- Yes
- Latitude/Longitude
- Null
- Horizontal Datum
- NAD 1927
- Source: How Located
- Other
- NFIP Community Name & Community Number
- Salem, City of & 410167
- State
- Oregon
- Map and Panel Number
- 41047C034
- Suffix
- H
- Firm Index Date
- 1/2/2003
- Firm Panel Effective/Revised Date
- April 30, 2010
- Flood Zone
- AE
- Base Flood Elevation
- 180.00
- Base Flood Elevation Source
- Engineer Determined
- Elevation Datum
- NGVD 1929
- Is this CBRS or OPA?
- No
- ROW Dedication Req'd?
- No
- Commercial Vehicle Trips
- 0
- New Impervious Area (sq ft)
- 0
Action Details
Agreements
-
PSFA
- Status:
- Approved
- Completed Date:
- 1/25/2022
- Assigned Staff:
- Jason Valyou
- View Details
Info
Application Intake
-
Assign Bin Number
- Status:
- Open
- Assigned Staff:
- PW Coordinator
Info
Final B&S Inspections
-
Regulatory Final
- Status:
- Approved
- Completed Date:
- 10/25/2024
- Assigned Staff:
- Matt Olney
- View Details
Info
Plan Review
-
DS Plan Review
- Status:
- Approved
- Completed Date:
- 1/26/2022
- Assigned Staff:
- Matt Olney
- View Details
-
Floodplain Development Review
- Status:
- Complete
- Completed Date:
- 1/20/2022
- Assigned Staff:
- Robin Dalke
- View Details
-
PW Make Ready To Issue
- Status:
- Ready to Issue
- Completed Date:
- 1/26/2022
- Assigned Staff:
- PW Coordinator
- View Details
Info
PW Environmental Services
-
Environmental Services Inspection
- Status:
- Approved
- Completed Date:
- 8/31/2023
- Assigned Staff:
- Environmental Services
- View Details
Info
PW Finals
-
Final Field Inspection
- Status:
- Approved
- Completed Date:
- 10/25/2024
- Assigned Staff:
- PW Inspector
- View Details
Info
PW Inspections
-
Sewer Tap Installation
- Status:
- Completed by City
- Completed Date:
- 2/24/2022
- Assigned Staff:
- PW Sewer
- View Details
-
Storm Inspection
- Status:
- Open
- Assigned Staff:
- PW Inspector
-
Driveway Inspection
- Status:
- Approved
- Completed Date:
- 8/17/2023
- Assigned Staff:
- Randy Riesterer
- View Details
-
Sidewalk Inspection
- Status:
- Approved
- Completed Date:
- 8/17/2023
- Assigned Staff:
- Randy Riesterer
- View Details
-
Elevation Certificate
- Status:
- Complete
- Completed Date:
- 9/28/2023
- Assigned Staff:
- PW Floodplain Manager
- View Details
-
Erosion Control Inspection
- Status:
- Approved
- Completed Date:
- 2/4/2022
- Assigned Staff:
- Randy Riesterer
- View Details
-
Initial Sewer Inspection
- Status:
- Closed
- Completed Date:
- 3/2/2022
- Assigned Staff:
- Randy Riesterer
- View Details
-
Sewer Inspection
- Status:
- Approved
- Completed Date:
- 8/17/2023
- Assigned Staff:
- PW Inspector
- View Details
Info
PW Water Inspections
-
Meter Installation
- Status:
- Complete
- Completed Date:
- 3/24/2022
- Assigned Staff:
- Donald Lovas
- View Details
-
Water Tap Installation
- Status:
- Completed by City
- Completed Date:
- 2/28/2024
- Assigned Staff:
- PW Water Group
- View Details
Info